Recent Projects

  • Albany Airport – Taxiway, RFDS Apron & Access Road – P17001
  • Norwood Road Widening & Reconstruction
  • Millbrook Road Widening & Reconstruction – C15023
  • Perkins Beach Road (SLK 0.5-1.7) Upgrade – C15032
  • Port Road Cycle Road Widening & Cycle Paths 1.6km – MRWA Fulton Hogan
  • Lot1002 Catalina Road Subdivision – Valley View Albany
  • Lot 50 Link Road Subdivision – Marbelup Investments
  • Millbrook Road Box Culvert Reconstruction – City of Albany
  • Pfeiffer Road Reconstruction C13017 – 1.4 km – City of Albany
  • Willyung Road Upgrade C13016 – 1.2 km – City of Albany
  • Mt Clarence – Anzac Road and Carpark upgrades – Wauters Enterprises
  • Reconstruction Lower Denmark Road C12003 – 2.7 km – City of Albany
  • Reconstruction Lower King Road C10015 – 1.2 km – City of Albany
  • CBH Terminal Albany – Roads and structural pads for Leighton’s Engineering
  • Earthworks & Demolition for Water Corporation at Mt Melville and Mt Clarence
  • Seawall Construction at Whaleworld and Emu Point.

 

 Recent Experience

Project

Type of Work

Duration

Personnel

Comment

Albany Airport – Taxiway, RFDS Apron & Access Road – City of Albany Construction of new taxiway, RFDS apron and access road. 8 weeks

Contract

P. Webster Sup’t.

H. O’Neill Project. Engr.

Completed On time

In budget

Norwood Road

City of Albany

Widening and Reconstruction of 1.3km Road 12 Weeks P. Webster Sup’t.

H. O’Neill Project. Engr.

Completed On time

In budget

Perkins Beach Rd

City of Albany

C150032

Realignment & construction of 1.2 km road 12 Weeks P. Webster Sup’t.

H. O’Neill Project. Engr.

Completed On time

In budget

Bayonet Head Shopping Centre Carpark and Drainage 32 Weeks P. Webster Sup’t. On time

In budget

Millbrook Rd Widening

City of Albany

C 15023

Widening and Reconstruction of 1.6km Road 12 Weeks P. Webster Sup’t.

H. O’Neill Project. Engr.

P. Nelson, Engr.

Completed On time

In budget